Built on 29 CFR Part 1926

OSHA 30 Construction Practice Test (Adaptive Mock)

The OSHA 30-Hour Construction course goes deeper than OSHA 10 and is aimed at supervisors. These questions follow the federal construction standards in 29 CFR 1926. Each attempt draws 15–20 questions and adapts to your last score.

Last updated · 201 original questions in this pool · Trade Exam Hub Editorial Team

Adaptive Practice Test

15–20 Questions Drawn From 201

Every attempt is a new test: questions are drawn at random and the answer order is shuffled. Score 80% or more and your next test moves up a level; score under 50% and it eases back. Your level is saved only in this browser.

Your Level Foundation

Take the Full Timed Mock Exam

How This Practice Test Works

These are original questions written by our editorial team from the published 29 CFR 1926. They are not real exam questions. Each question cites the 29 CFR section behind the answer. OSHA does not endorse Trade Exam Hub, and outreach cards come only from authorised trainers.

What the Question Pool Covers

Every question cites the rule behind its answer. Counting those references shows where the pool puts its weight:

ReferenceQuestions
29 CFR 1926.12027
29 CFR 1926.250(b)5
29 CFR 1926.350(a)3
29 CFR 1926.701(b)2
29 CFR 1926.754(b)2
29 CFR 1926.14272
29 CFR 1926.14312
29 CFR 1926.251(a)2
29 CFR 1926.302(b)2
29 CFR 1926.304(b)2
29 CFR 1926.1052(c)2
29 CFR 1904.392
29 CFR 1926.404(b)(1)(iii)2
29 CFR 1926.1153 Table 12
29 CFR 1926.150(c)(1)(i)2
29 CFR 1926.102(a)(2)2
OSHA safety rules1
29 CFR 1926.12041
29 CFR 1926.701(d)1
29 CFR 1926.701(c)1
29 CFR 1926.701(a)1
29 CFR 1926.701(f)1
29 CFR 1926.760(a)1
29 CFR 1926.760(b)1
29 CFR 1926.760(c)1
29 CFR 1926.350(d)1
29 CFR 1926.350(f)1
29 CFR 1926.351(b)1
29 CFR 1926.14241
29 CFR 1926.251(c)1
29 CFR 1926.300(d)1
29 CFR 1926.300(b)1
29 CFR 1926.1052(a)1
29 CFR 1926.62(c)1
29 CFR 1926.62(b)1
29 CFR 1926.62(j)1
29 CFR 1926.21(b)1
29 CFR 1926.20(b)1
29 CFR 1926.25(a)1
29 CFR 1926.341
29 CFR 1926.11531
29 CFR 1926.1153(g)1
29 CFR 1926.652(a)1
29 CFR 1926 Subpart P1
29 CFR 1926.502(d)1
29 CFR 1926.451(g)1
29 CFR 1926.521
29 CFR 1926.150(c)1
29 CFR 1926.502(d)(16)(ii)1
29 CFR 1926.502(d)(16)(iv)1
29 CFR 1926.502(d)(16)(iii)1
29 CFR 1926.502(d)(3)1
29 CFR 1926.502(d)(4)1
29 CFR 1926.502(d)(12)1
29 CFR 1926.502(d)(13)1
29 CFR 1926.502(c)(1)1
29 CFR 1926.502(c)(7)1
29 CFR 1926.502(c)(4)(i)1
29 CFR 1926.502(c)(8)1
29 CFR 1926.502(e)(2)1
29 CFR 1926.502(f)(1)(ii)1
29 CFR 1926.502(f)(2)(ii)1
29 CFR 1926.502(f)(2)(iii)1
29 CFR 1926.502(g)(1)(i)1
29 CFR 1926.502(g)(2)(i)1
29 CFR 1926.502(g)(3)(iii)1
29 CFR 1926.502(j)(2)1
29 CFR 1926.502(j)(3)1
29 CFR 1926.502(j)(6)(i)1
29 CFR 1926.502(b)(5)1
29 CFR 1926.502(d)(10)(ii)1
29 CFR 1926.451(a)(3)1
29 CFR 1926.451(a)(5)1
29 CFR 1926.451(b)(2)1
29 CFR 1926.451(b)(2)(i)1
29 CFR 1926.451(b)(3)1
29 CFR 1926.451(b)(3)(ii)1
29 CFR 1926.451(b)(4)1
29 CFR 1926.451(b)(7)1
29 CFR 1926.451(c)(1)(ii)1
29 CFR 1926.451(e)(2)(ii)1
29 CFR 1926.451(e)(2)(iii)1
29 CFR 1926.451(e)(8)1
29 CFR 1926.451(e)(6)(i)1
29 CFR 1926.451(e)(6)(ii)1
29 CFR 1926.451(g)(4)(ii)1
29 CFR 1926.451(g)(4)(vi)1
29 CFR 1926.451(e)(4)(xi)1
29 CFR 1926.451(f)(6)(ii)1
29 CFR 1926.451(d)(1)1
29 CFR 1926.1053(a)(3)(i)1
29 CFR 1926.1053(a)(3)(ii)1
29 CFR 1926.1053(a)(4)(ii)1
29 CFR 1926.1053(a)(13)1
29 CFR 1926.1053(a)(19)1
29 CFR 1926.1053(a)(22)(iii)1
29 CFR 1926.1053(a)(24)1
29 CFR 1926.1053(a)(1)(iii)1
29 CFR 1926.1053(a)(1)(i)1
29 CFR 1926.1052(a)(4)1
29 CFR 1926.1052(c)(6)1
29 CFR 1926.1052(c)(5)1
29 CFR 1926.1052(c)(11)1
29 CFR 1926.1052(c)(3)(iv)1
29 CFR 1926.651(c)(2)1
29 CFR 1926.651(g)(1)(iii)1
29 CFR 1926.651(l)1
29 CFR 1926.651(b)(2)1
29 CFR 1926.652(b)(1)(i)1
29 CFR 1926.652(g)(2)1
29 CFR 1926.652(a)(1)(i)1
29 CFR 1926.404(c)(1)(ii)(D)1
29 CFR 1926.404(c)(1)(ii)(A)1
29 CFR 1926.404(c)(1)(iii)1
29 CFR 1926.405(a)(2)(ii)(G)1
29 CFR 1926.405(b)1
29 CFR 1926.405(j)(1)(ii)1
29 CFR 1926.405(c)(3)(ii)1
29 CFR 1926.405(a)(2)(iii)1
29 CFR 1926.405(a)(2)(ii)(A)1
29 CFR 1926.1417(s)1
29 CFR 1926.1417(o)(2)1
29 CFR 1926.1431(j)(1)1
29 CFR 1926.1431(n)1
29 CFR 1926.1431(e)(10)1
29 CFR 1926.1431(e)(6)1
29 CFR 1926.1408(a)(2)(ii)1
29 CFR 1926.1408(b)(3)1
29 CFR 1926.151(c)(1)1
29 CFR 1926.151(c)(2)1
29 CFR 1926.151(c)(5)1
29 CFR 1926.151(d)(5)1
29 CFR 1926.151(d)(7)1
29 CFR 1926.62(d)(6)1
29 CFR 1926.62(d)(6)(iii)1
29 CFR 1926.62(j)(2)(iv)(A)1
29 CFR 1926.62(j)(3)(i)(A)1
29 CFR 1926.62(j)(2)(i)(A)1
29 CFR 1926.62(g)(2)(i)1
29 CFR 1926.1101(c)(2)1
29 CFR 1926.1101(g)1
29 CFR 1926.1101(g)(5)1
29 CFR 1926.1101(k)(3)(iii)1
29 CFR 1926.1153(h)(2)1
29 CFR 1926.1153(h)(6)(i)1
29 CFR 1926.1153(c)(1)1
29 CFR 1926.1153(a)1
29 CFR 1926.600(a)(6)(iii)1
29 CFR 1904.39(a)(1)1
29 CFR 1904.39(a)(2)1
29 CFR 1926.350(a)(10)1
29 CFR 1926.350(a)(1)1
29 CFR 1926.350(f)(2)1
29 CFR 1926.352(d)1
29 CFR 1926.150(c)(1)(vi)1
29 CFR 1926.150(c)(1)(ii)1
29 CFR 1926.601(b)(4)1
29 CFR 1926.200(d)1
29 CFR 1926.201(a)1
29 CFR 1926.28(a)1
29 CFR 1926.300(b)(5)1
29 CFR 1926.1031
29 CFR 1926.703(b)(10)1
29 CFR 1926.760(a)(1)1
29 CFR 1926.760(b)(1)1
29 CFR 1926.760(c)(3)1
29 CFR 1926.760(c)(5)1
29 CFR 1926.754(b)(2)1
29 CFR 1926.754(b)(3)1
29 CFR 1926.1203(d)1
29 CFR 1926.1205(e)(1)1
29 CFR 1926.350(a)(11)1
29 CFR 1926.302(b)(8)1
29 CFR 1926.300(d)(3)1
29 CFR 1926.601(b)(9)1
29 CFR 1926.52(a)1

Sample Questions With Worked Answers

A few questions from the pool with the answer and explanation, so you can see the style before you start.

  1. Who is the OSHA 30-hour construction course designed for?

    Answer: Supervisors and workers with safety responsibility. OSHA describes the 30-hour course as more in-depth training for supervisors and workers with some safety responsibility.

    Reference: OSHA Outreach Training Program

  2. Under the confined spaces standard, a confined space is large enough to bodily enter, has limited means of entry or exit, and:

    Answer: Is not designed for continuous employee occupancy. 1926.1202 definition.

    Reference: 29 CFR 1926.1202

  3. A permit-required confined space has one or more hazards, such as:

    Answer: A hazardous atmosphere, engulfment material, a trapping configuration or another serious hazard. 1926.1202 definition of permit space.

    Reference: 29 CFR 1926.1202